スケジュール短縮

すけじゅーるたんしゅく · Schedule compression

A technique for shortening the project schedule without reducing scope, primarily by parallelizing tasks that were originally planned in sequence (fast-tracking) or by adding resources to critical-path activities (crashing). Reducing the duration of critical-path work is the most effective approach.

Past questions testing this term · 1 questions

  • 2009h21a #51プロジェクトのスケジュールを短縮する方法について説明したものはどれか。