ネットワーク図
ねっとわーくず · Network diagram (Arrow diagram)
Also known as: アローダイアグラム / クリティカルパス
A project management diagram that uses arrows and nodes to represent the sequence of tasks and their durations, also known as an arrow diagram. It is used to identify the critical path and determine the shortest possible project completion time. By comparing total durations across all paths, project managers can see which tasks, if delayed, will impact the overall schedule.
Past questions testing this term · 1 questions
- 2009h21h #37図の作業について、全体の作業終了までの日数は24日間であった。作業Cの日数を3日短縮できたので、全体の作業終了までの日数が1日減った。作業Dの所要日数は何日か。…